An office is considering a move. This worked example shows what can be checked before a large commitment, and where a responsible report must stop. All people, amounts and events are illustrative.
Synthetic material only. Not a real client case or a promise of results.
The sample shows one complete report format. It does not mean every consultation includes every chapter. The scope examples separate the main document, attachments, discussion and follow-up that need to be agreed.
SANRUI / WORKED REPORTSR-DEMO-01 · 1/5 · Synthetic example
Question, scope and initial position
Example question: “We have orders, but cash arrives slowly and meetings are often interrupted. Should we move the office?”
Record status
Entirely synthetic. No real company, client, chart or realised outcome is represented. Figures are illustrative, not an audit.
Scope
Compare a move with changes to current work arrangements. No investment, legal, structural or clinical advice.
Initial position
Do not commit to a move on the information available. First separate payment status from meeting disruption and clarify the missing spatial inputs.
Missing inputs
Verified orientation, occupancy history, a measured floor plan, contract terms, customer responses and comparable operating records.
SANRUI / WORKED REPORTSR-DEMO-01 · 2/5 · Synthetic example
Inputs and what they establish
Payment items to check, in CNY 10,000
Item
Amount
Status at review
A
Amount40
Status at reviewAccepted; 16 days overdue
B
Amount30
Status at reviewAccepted; due in 7 days
C
Amount20
Status at reviewAcceptance incomplete; payment condition not met
D
Amount10
Status at review9 days overdue; amount disputed
The four illustrative amounts sum to 100. This is a list of payment items, not a statement that every item is a recognised accounting receivable. Only A and D are overdue, totalling 50; 10 of that is disputed. Verify the actual contract and ledger before applying these labels.
A second illustrative record has six meetings, four interrupted by deliveries or passing staff. That small sample suggests a room-use question worth checking; it does not establish an effect on sales or payments.
Can establish
Which payment items need acceptance, collection or dispute handling; when and where interruptions occurred.
Cannot establish
That the office caused delayed payments, that a move will help, or that traditional chart relationships have been scientifically validated.
SANRUI / WORKED REPORTSR-DEMO-01 · 3/5 · Synthetic example
Traditional reading and competing explanations
Xuan Kong considers orientation, period and the distribution of Flying Stars. In this sample those inputs are not verified, so there is no claimed chart, favourable direction or relocation date. A doorway is first mapped as an actual entrance with observable traffic, not assigned an invented auspicious label.
A Zi Wei assessment would require the relevant person’s birth inputs and permission; a Qi Men assessment would need a defined question and an actual recorded chart time. Neither is fabricated here merely to make a combined report look complete.
Hypotheses to compare
Possibility
Evidence needed
What weakens it
Payment workflow
Evidence neededAcceptance records, due dates and responsibility for each item
What weakens itMost delayed items are instead tied to customer disputes or contractual conditions
Room-use interference
Evidence neededConsistently recorded interruption type and timing
What weakens itInterruptions remain unchanged after a limited rearrangement
Customer-side conditions
Evidence neededActual reasons given, contract terms and payment commitments
What weakens itCustomers confirm a different reason supported by records
Assumptions to confirm, not silently adopt
Permission
The decision owner and affected staff can approve the trial; building and contract requirements are met.
Comparable evidence
Meeting counts, interruption definitions and payment items can be compared without mixing different populations.
Costs and timing
A real deadline permits the trial, its time cost is acceptable and an agreed stopping point exists.
SANRUI / WORKED REPORTSR-DEMO-01 · 4/5 · Synthetic example
Options, costs and first actions
Four options, no assumed improvement
Option
Cost or limitation
Decision condition
Stay as-is
Cost or limitationNo relocation cost; current issues remain to be clarified
Decision conditionReasonable while essential records are missing
Limited trial
Cost or limitationStaff time; no structural work or blocked exits
Decision conditionTry scheduled deliveries and a meeting no-interruption period; assign payment follow-up separately
Move
Cost or limitationRent, fit-out, downtime and management effort
Decision conditionOnly reconsider after comparing actual operating needs and verified costs; never on a chart alone
Relevant assessment first
Cost or limitationProfessional review time and fees
Decision conditionChoose this before a trial where safety, contract or specialist requirements are unresolved
Record owner: reconcile A–D against the original records and separate accepted amounts from disputed or unaccepted work.
Office coordinator: record a comparable baseline, then try the limited meeting arrangement without changing unrelated procedures at the same time.
Decision owner: agree the trial duration, its cost ceiling and review date in advance. These are planning choices, not predicted dates of improvement.
SANRUI / WORKED REPORTSR-DEMO-01 · 5/5 · Synthetic example
Review record and grounds for changing course
Blank review record, to be completed after observation
Measure
Baseline
Follow-up
Meeting interruption rate
Baseline4/6 in the synthetic input; sample too small for a firm conclusion
Follow-upInterrupted meetings / comparable meetings, using the same definition
Overdue amount
Baseline50 in the synthetic input, including 10 disputed
Follow-upOriginal overdue items recovered; new overdue items listed separately
Acceptance backlog
Baseline20 awaiting acceptance in the synthetic input
Follow-upItems accepted and unresolved reasons; do not count as recovered cash
Cost and adverse effects
BaselineNot yet measured
Follow-upTime, spending, disruption or complaints caused by the trial
Review has not happened. A blank result is not a positive outcome. If the trial does not help, check the original hypothesis, external changes, comparable sample size and implementation. Consider reversing the change; do not extend the deadline indefinitely to preserve the original interpretation.
Even a later improvement would not by itself prove a traditional explanation caused it. This website does not publish original client materials or real consultation records. Public samples do not quote clients or demonstrate achieved outcomes.
Longer-term costs and a reason to stop
Include recurring coordination, staff disruption and the cost of reversing a move. Record who bears those costs. If the original problem does not improve at the agreed review, or adverse effects outweigh the benefit, reassess or stop; do not keep adding paid adjustments to preserve the original explanation.